Introduction | Historical Background | Chronology | Geography | Biography | Technology | Ownership and Financing | General Bibliography |
Southwestern
States |
Missouri | Saint Louis | Report of Water Works Committee |
St. Louis
Beacon, May 26, 1831.
Extract from the
proceedings of the Board of Aldermen of the City of St. Louis, May 20,
1831.
The Committee on Water Works, submitted the following Report, which was
read, and on motion of Mr. Simpson, ordered that the Register cause the
same to be published, To wit:-
The Committee appointed by the Board of Aldermen of the City of St. Louis,
on the subject of the Water Works now in progress near said City,
Report: That is appears, that on the 17th day of September, 1829, an
agreement was entered into, between the corporate authorities of the city
and Messrs. John C. Wilson and Abraham Fox, by which the authorities
aforesaid, in behalf of the city, engaged to furnish said Wilson & Fox
with a lot of ground, on the bank of the river Mississippi, of forty by
one hundred and twenty feet, and with half an acre of ground of some
eminence, not further than the large mound on the land of Gen. William H.
Ashley, or thereabouts; and to pay said Wilson & Fox the sum of three
thousand dollars, whenever the water should have been delivered to the
reservoirs; and that the said Wilson & Fox were to have the sole and
exclusive privilege of supplying the city of St. Louis with water, and
were to receive all the emoluments to be derived therefrom for the term of
twenty-five years from that date; that said Wilson & Fox were to
deliver water in the reservoirs, and supply part of the hydrants that were
to be erected, within fifteen months, and were to supply the residue
within eighteen from, from that time. The first of these periods elapsed
on the 17th day of December, 1830, and the later on the 17th of March,
1831.
On the 17th day of August, 1830, the said John C. Wilson sold out and
transferred to said Fox, all his right, title and interest in the said
Water Works, and the contract then become between the city and the said A.
Fox, as sole contractor. In pursuant of the contract on the part of
the city authorities, they, on the 3d day of April, 1830, purchased from
William H. Ashley, for the sum of $500, a lot, including the mound, near
the northwestern corner of the tract of land on which is the residence of
said Ashley. On the 29th of June, in the same year, they also
purchased from Col. Geo F. Strother, as agent of the United States, four
lots, forming a Block or Square on the bank of the river Mississippi, for
the sum of $2265--the former of which lots was intended and appropriated
for a reservoir for the clarified water, and the latter for a reservoir
for the water when first drawn from the river, and as a site for the
erection of an engine-house. It appears also that the city
authorities have advanced to said contractor, as per his receipt of
November 4th, 1830, the sum of $1000, as part of the sum of $3000 which
was to have been said when the water should have been delivered in the
reservoir--for which he agreed to pay interest, at the rate of 8 per cent.
per annum, until the contract should have been complied with on his part,
by the delivery of the water in the reservoir, as before mentioned.
It further appears, that an additional sum of $500 has been advanced to
said contractor out of the funds of the city, making a total of advances
made to him, of $1500. The Mayor and a Committee of the Board of
Aldermen, on the 2d day of April last, also gave to Messrs. A. W. Vanleer
and Co. their note, in behalf of the city, for the sum of $2309.60 cents
for iron pipes furnished by them, for the use of the Water works, which
will become payable on the 1st day of April, 1832. On the 29th day
of March last, a contract was entered into by the Mayor, on the part of
the city, in virtue of a Resolution of the Board of Aldermen for the 22d
of the same month, with Messrs. Vanleer and Co. for a further supply of
iron pipe; and the city, is by that contract, responsible for 2000 feet of
six-inch iron pipe, and 5000 feet of iron pipe four inches in diameter
--the probable amount of which, calculating the pipe of six inches in
diameter at $1.90 cents per foot, and that of four inches at $1.40 cents
per foot, will amount of ten thousand eight hundred dollars.
Your Committee would here observe, that (if it can be procured) it will be
necessary to purchase from Gen. Ashley, a small portion of ground to the
south and east of that already bought from him, which may be estimated to
cost some two or three hundred dollars, say $300; so that the advances
made by the city on account of the sites for the Water Works, for what it
will be necessary to purchase, are--
For lot at corner of Gen. Wm. H. Ashley's tract, | $500.00 |
" lot bought of Col. Strother as agent of the U.S., on the bank of the Mississippi, | $2265.00 |
Amounting to | $2765.00 |
Necessary for the purchase of land from General Ashely, | $300.00 |
So that if the Board
should agree with the Committee in thinking it necessary to purchase the
additional piece of land from General Ashley, and he should agree to sell,
there will be an additional sum of $300 required for that purpose, and the
sum expended by the city for the purchase of land, on which to erect the
buildings and reservoirs of the Water Works, will then amount to $3065.00.
The sum advanced to Messrs Vanleer & Co. payable on 1st April, 1832, without interest, is | $2309.60 |
So that the whole amount advanced by the city authorities, and that for which is city is bound, by the note aforesaid, exclusive of the cost of lots purchased and to be bought, and exclusive of the contract with Messrs. Vanleer & Co., is | $3809.60 |
And if the land proposed to be bought be purchased, will amount to | $6874.60 |
In a Report made by a
Committee of the preceding Board of Aldermen in conjunction with the
Mayor, which Report is endorsed 25th March 1831, it was recommended that
the city should take three-fourths of the stock of the Water Works, and of
course pay three-fourth of the stock of their erection -- which was, as
your committee were informed, asked for by Mr. Fox, and agreed to by him
and by the Board of Aldermen, and approved of by the Mayor; and a written
contract has been made between the city authorities and Mr. Fox, in
conformity with the recommendation of that Committee. The Board of
Aldermen also passed a Resolution authorizing the Mayor to contract for a
loan of $20,000, to provide the means of carrying into effect their parts
of the agreement; but to give the Mayor legal authority to contract for
the loan, an ordinance for that purpose will be necessary. Your
Committee are not informed whether Mr. Fox has given any security that his
part of the agreement would be complied with, other than is contained in
the articles of agreement before referred to.
The Contractor, on his part, has excavated the reservoir on the mount,
which is intended to be 64 feet by 58 in the clear, and 12 feet in
depth--has built the surrounding stone wall to a height of above 5 1/2
feet, and is now paving the bottom thereof, having laid the plank flooring
underneath, supposed to be necessary. The engine-house, on the lot
of the bank of the river, is built, and the engine, and part of the
necessary machinery appurtenant thereto, has been fixed therein. The
reservoir on the bank of the Mississippi, and near the engine-house has
been excavated to the rock, which is about 6 feet from the surface of the
earth. It is intended to blow the rock, so as to make said reservoir
to the depth of 12 feet, at least; and it is to be 40 by 80 feet in the
clear. The ditch in which the conduit or pipe is to be placed,
communicating between the reservoirs, has been dug, and a considerable
quantity of iron pipes, obtained from Messrs. Vanleer & Co., are on
the ground; and, so far as the work has yet advanced, your Committee are
of the opinion that it is faithfully executed, and, as well as they are
capable of judging, calculated to attain the end desired.
Your Committee would remark that the reservoir on the river, being
intended to be 40 feet by 80, and the walls 12 feet in height, will, when
filled to a depth of 10 feet, contain about 239,000 gallons. The
reservoir on the mound is 64 by 58 feet, and, if filled to the same depth,
will contain about 278,000 gallons. The contractor states, that the
forcing pump provided will raise about 400 gallons of water per minute, so
that the forcing pump would fill the largest reservoir, to the depth of 10
feet, in about eleven hours and a half; and were the reservoir on the
mound filled to the height before mentioned, it would supply 9266 families
for one way, allowing each family to consist of 7 persons, and at the rate
of 30 gallons of the family that period.
According to the present arrangement, it is intended that the main conduit
shall extend from the mount no farther down Third-street than to a point
near the corner of the old bastion; from thence a pipe is to be laid down
the cross street, north of the bastion, into the Main-street, and then
down Main-street 4367 feet. Your Committee would suggest for
consideration, the expediency of some alteration in this respect, so as to
take the largest conduit in a straight line down Third-street, as far as
it may at present be thought proper to extend it--say as far as the
Hospital--and to place lateral pipes in such cross streets between Third
and Main-streets, as may be thought necessary. By placing the
conduit in Third-street at this time, a great additional expence would be
saved, which would necessarily have to be incurred should that measure be
delayed until Third-street shall have been paved; and the immediate
facility of supplying a much larger number of families with water would be
afforded, which would of course greatly increase the revenue to be derived
from it. The contractor, in an estimate submitted to the Committee
by him, and hereinafter referred to, estimates the cost of removing and
replacing the stone pavement on Main street, as far as the pipe is
intended to be placed therein, and inclusive of the cost of excavating the
ditch, at the sum of $2095, which is rather more than one-third of the
estimated cost of the iron pipes to be laid in the same distance.
Mr. Fox was requested by your Committee, to furnish them an estimate of
the cost of the Water Works, from their commencement to their completion,
so far as at present intended, which he has done, and is herewith
submitted as part of this report, and is marked A No 1--by which it
appears that he estimates that the whole cost at $30,441.96 cents, and
that there has been expended the sum of $4,566.00. As in estimates
of expenditures to so great an extend, the contractor suggested, and your
Committee concur with him in opinion, that some allowance ought to be
made, we have thought it highly probable that the cost will be at least
$35,000, and therefore estimate it at that sum. To place the subject
before you in as small a compress as we can, you Committee make the
following recapitulation and statement of the estimated cost of the work,
the sum necessary to be provided by the city to defray the cost of that
part of the work agreed to be done by them; an estimate of the necessary
expenditures per annum, after the work is completed as is at present
intended; the estimated receipts therefrom, and the whole cost to the
city:
Estimated cost of Water Works, | $35,000 |
Three-fourths of which is to be paid by the city, is | $26,250 |
Superintendent's salary as per last agreement above mentioned, estimated at | 500 |
The sum therefore to be paid by the city, will be | $26,750 |
If the expenditures made,
and to be made in a partnership point of view, so far as they can be
considered in that light, the estimated cost will be as follows: Estimated
cost of Water Works, $35,000--three fourths of which to be paid by the
city, $26,250; estimated cost of the city's part of superintendent's
salary, 500; Total $26,570. The sum advanced $1500; which deducted
from that sum, leaves $25,250.
The one-fourth cost to be paid by Mr. Fox, is $8,750; the whole sum
expended, according to contractor's statement, is 4566; from which take
the sum advanced by the city, 1,500--leaves, at the sum advanced by Mr.
Fox, 3,066, and the sum necessary on his part is 5,684.
Statement of the estimated cost of the work, the sum necessary to be
provided by the city to defray the cost of that part of the work agreed to
be done by them; an estimate of the necessary expenditures per annum,
after the work is completed as is at present intended; the estimated
receipts therefrom, and the whole cost to the city:
Estimated cost of Water Works, | $35,000 |
Three-fourths of which is to be paid by the city, is | $26,250 |
Estimated Expense per Annum. | |
Interest on $25,250, calculated to be raised by a loan at 6 per cent interest, | $1,515,00 |
Superintendent's salary (exclusive of his fourth interest,) as proposed in the Report of the Committee of the preceding Board, endorced 25th March, 1831; | 600.00 |
Hire of workmen, fuel for engine, &c. at $5 per diem, $1,825--three-fourths of which is | 1,368.75 |
$3,483.75 |
Your Committee have
made no estimate for repairs, as they have no means of judging to what
extent they may be necessary, or their probable cost.
Estimated Revenue. | |
On the supposition that pipes will be laid down Main street, from the corner of the cross street north of the bastion to the point before mentioned, the receipts for the first year have been estimated on the basis that 200 families would take water, and that they would have $20 each, and would be | $4,000. |
Another estimate has been made on the supposition that each square would contribute, on the average, $100; and their being 26 squares in the distance above-mentioned, this estimate would make it amount of | $2,600. |
Taking the first estimate, the proportion accruing to the city would be | $3,000.00 |
And taking the latter, it would be | $1,950.00 |
Your committee suppose it
is possible to derive some emolument from the application of the surplus
power of the steam-engine to other purposes; but they have not been
enabled to calculate how much power could be spared, nor to estimate the
amount of the receipts to be derived from that source.
The Whole Cost to the City
|
|
Purchase of lot from Wm. H. Ashley | $500.00 |
do additional, | 300.00 |
do from G. F. Strother, | 2,265.00 |
Cost of three-fourths of Water Works, &c. | 26,250.00 |
Superintendent's salary, | 500.00 |
$29,815.00 |
All of which is respectfully submitted. J. Warner, Chairman. St. Louis, May 20, 1831.
Agreeable to the request of a Committee of the Board of Aldermen of the City of St. Louis, I herewith submit an estimate of the probable cost of the Water Works:
FIRST DIVISION | ||
Engine, pumps, and charges, | $1,800.00 | |
Engine-house, | 1,000.00 | |
Extra pipes and wheels to engine, | 500.00 | |
Cost of patterns for wheels and pipes, | 500.00 | |
Digging, blowing, and removing earth and stone from reservoir at river, | 507.00 | |
Walling said reservoir, grouting, and connecting the same with engine, | 1,354.00 | $5,661.00 |
SECOND DIVISION | ||
Excavating ditch from river to reservoir on mound, 277 cubic yards, | $46.17 | |
Blowing rock, from river, through engine-house to Main-street, and seat for fly-wheel, | 95.00 | |
Excavating reservoir on mound, and removing earth, 2022 cubic yards, a 20 | 404.40 | |
14,787 plank on botton reservoir, $2.00 | 295.74 | |
Nails, corking and laying the same, | 307.91 | |
1400 brick, and laying the same, | 231.00 | |
Grouting over the same with cement, | 65.00 | |
Cement lime, | 150.00 | |
Wall of said reservoir, 461 perch $2 | 928.00 | |
1236 feet pipe from river to reservoir, $1.87, | 2,311.32 | |
2790 lbs. lead for 155 joints pipe a 3 | 83.70 | |
Joining and soldering 155 joints pipe, a 50 | 77.50 | |
Filling ditch and packing 154 pipe a 25 | 38.50 | |
5 stop cocks and appurtenances thereto, | 100.00 | |
Walling mound, 500 perch, | 1,000.00 | |
Soding between the two walls, | 200.00 | |
Enclosing reservoir, | 300.00 | $6,634.24 |
THIRD DIVISION | ||
Digging ditch from mound to cross street, passing by McQueen's,* 2467 feet, | 91.00 | |
5544 lbs. lead for 308 joints pipe, a 3 | 166.32 | |
Joining pipes, and packing, 308 a 75 | 231.00 | |
17 stop cocks and appurtenances thereto, | 340.00 | |
4 walls closing said stop cocks, (centre of streets,) | 60.00 | |
2467 feet pipe, $1.87 | 4,634.50 | $5,522.82 |
FOURTH DIVISION | ||
Digging ditch down and cross street, by McQueen's, to Main-street, 833 feet, | 27.00 | |
833 feet, 4 inch. pipe, a 1.40 | 1,166.20 | |
1,400 lbs. lead, 140 joints pipe, a 3 | 42.00 | |
Joining 140 pipes, and packing ditch, a 75, | 105.00 | |
8 stop cocks, 2 fire plugs and appurtenances, | 210.00 | |
2 walls enclosing fire plugs, | 30.00 | $1,580.20 |
FIFTH DIVISION | ||
Down main steet, opposite hospital, 4367 feet, removing and replacing 340 sqr. stone, | 2,004.00 | |
Excavating ditch down same, | 97.00 | |
4,367 feet, 4 in. pipe @ 1.40, | 6,113.80 | |
7280 lbs. lead for 728 joints pipe, a 3 | 218.40 | |
Joining 728 pipes and packing ditch, a 75 | 546.00 | |
48 stop cocks, & 12 fire plugs, &c, | 1,260.00 | |
12 walls enclosing same, | 180.00 | $10,509.20 |
SIXTH AND LAST DIVISION | ||
Ditch from main street to hospital, 833 feet, | 23.00 | |
833 feet, 1-2 in. lead pipe, a 50 | 416.50 | |
Laying pipe and filling ditch, | 70.00 | |
Hydrants at hospital, | 25.00 | 534.50 |
$30,441.96 | ||
Already expended, | 4,566.00 | |
$25,878.96 |
It would be well to bear
in mind, that, in executing a work of this magnitude, many contingent
expenses will occur to a considerable amount, which, in making an
estimate, it is impossible to enumerate.
Yours, respectfully, A. FOX. May 13, 1831.
Gentlemen of the
Commmittee. A true abstract.--Attest, J. A. Wherry, Register.
© 2016 Morris A. Pierce