Portsmouth was incorporated as a town in 1815 and as a city in 1851.
The city built a Holly water system that began service on February 22, 1872, pumping water from the Ohio river using a steam-driven Holly gang and rotary pumps. The Common Council considered selling the system in 1889, but instead several new pumps were added starting in 1890 and a new plant was opened in 1914.
Water is supplied by the city of Portsmouth.
References
1870 "An ordinance
ordering the construction of water works, and establishing trustees of
the same," Portsmouth Daily Times, December 17, 1870, Page
2.
1871 "The Water Works," Portsmouth Times, June 3, 1871, Page 2.
1872 Portsmouth
Daily Times, February 24, 1872, Page 3.
The water works gave an exhibition of their works on the 22d at the water
works, the corner of Fourth and Court and in front of the Times
office. Water was thrown thirty feet above the top of Massic
Block. Citizens were generally well pleased.
1872 "Report of the Trustees of Water Works to the City Council," Portsmouth Times, May 11, 1872, Page 2. Also by-laws, regulations, and rates.
1872 "Water
Works Items," Portsmouth Times, October 19, 1872, Page 3.
Material is kept in readiness to start the rotary pumps at a moment's
warning.
1882 Portsmouth, from Engineering News 9:289 (August 19, 1872)
1882 Portsmouth
from "The Water-Supply of Certain Cities and Towns of the United States,"
by Walter G. Elliot, C. E., Ph. D.
1888 "Portsmouth,"
from Manual of American Water Works,
Volume 1.
1889 "Sober
Thoughts," Portsmouth Times, September 28, 1889, Page 1. | Part 2 | Editorial
|
About the Transfer of the City Water Works.
1890 "Portsmouth," from Manual of American Water Works, Volume 2.
1891 "Portsmouth," from Manual of American Water Works, Volume 3.
1897 "Portsmouth," from Manual of American Water Works, Volume 4.
1909 Fourth
Annual Report of the Commissioner of Health of the Commonwealth of
Pennsylvania, Part 2.
Page 1436: Portsmouth, Ohio water works.
1916 A
Standard History of the Hanging Rock Iron Region of Ohio: An Authentic
Narrative of the Past, with an Extended Survey of the Industrial and
Commercial Development, Volume 1, by Eugene B. Willard
Pages 170-171: Portsmouth. Founding the First Waterworks. The
long agitation for a city system of waterworks gave birth to the passage
of an ordinance, in December, 1870, which provided that it should be
established on the Holly plan of water-supply and fire-protection. The
founding of the works was placed in the hands of three trustees, specially
elected for the purpose—Phillip H. Kelly, Charles S. Green and Lewis C.
Robinson. On March 3, 1871, an ordinance was passed which “set apart and
appropriated that part of the public landing, so called and known, as lies
between the old corporation line and the east line of Gay street and
between Mill street and the Ohio river” to the uses of the waterworks
trustees; and thereon was constructed the necessary machinery. The
contract for constructing the works complete, which were ready for use in
April, 1872, was given to Weir and Overdale. On May 8th of that year, the
trustees of the waterworks reported that the total cost of the
installation of the system had been $132,291.13; that there were nearly
eight and a half miles of mains and 16,114 feet of service pipe.
The growing city required an enlargement of the works in every department,
so that by the middle ’80s nearly twenty miles of pipe was in service,
with about thirteen hundred hydrants, of which some ninety were for the
use of the fire department. Although a vast improvement over the public
wells, the old waterworks were very imperfect and unsatisfactory; but they
filled the bill, in a way, for a period of forty years.
Building of the Present Water System. In 1908 there was a general
demand for a new system of waterworks, and the common council appointed a
committee of citizens to study the needs of the community with reference
thereto. After three years a decision was reached and the proposed plan
was submitted to the State Board of Health. That body recommended minor
changes as to location and nature of installation; it was upon the
recommendation of the state board that the reservoir was placed on
Timmonds Hill and the general location of the plant fixed at its present
site on the banks of the Ohio River, five miles east of the city.
The committee of citizens, by whom the original investigations were
conducted, resigned, and the common council, as a body, built the works.
The contracts were let in August, 1911, and, on account of vexatious
delays, the works were not completed until after about three years; and
there are still defects which experts claim should be remedied, in order
to guarantee the city against a shortage of water in case of a break in a
main.
The pumping station and the filtering plant are on the river bank, a
quarter of a mile apart, and the clear-water basin, or purifying station,
on Timmonds Hill, not far to the northwest. The general plan of
distribution includes a direct connection of this outlying plant with the
City of Portsmouth, which is encircled by a belt of water pipes.
The total value of the Portsmouth system of waterworks as now installed is
estimated at $750,000. Adam Frick, the present mayor of Portsmouth, has
been a leader in the founding of the waterworks now in commission.
1935 "Kentucky
Tax," The Cincinnati Enquirer, October 19, 1935, Page 14.
Must be paid on City Property, Portsmouth City Council is told by
attorney.
1937 Seventeenth
Annual Report of the Ohio Conference on Water Purification,
held at Cincinnati on October 21 and 22, 1937
Page 75: Portsmouth Water Works in the 1937
Flood, by H. C. Growdon.
On January 13th, the stage of the Ohio River at Portsmouth was 38 feet and
steadily rising. On January 22nd it had reached a stage of 64 feet, water
had entered